First Beam Commissioning of the 400 MHz LHC RF System (2009)
Butterworth, A C, Angoletta, M E, Arnaudon, L, Baudrenghien, P, Bohl, T, Brunner, O, ...
Hardware commissioning of the LHC RF system was successfully completed in time for first beams in LHC in September 2008. All cavities ware conditioned to nominal field, power systems tested and all...
Hardware and Initial Beam Commissioning of the LHC RF Systems (2009)
Linnecar, T, Angoletta, M E, Arnaudon, L, Baudrenghien, P, Bohl, T, Brunner, O, ...
Hardware commissioning of the LHC RF Systems, the ACS Superconducting RF systems, ADT Transverse Dampers and APWL Wideband Longitudinal Monitors, started in late 2007 and was completed in time for...
Commissioning of the 400 MHz LHC RF System (2008)
Ciapala, Edmond, Arnaudon, L, Baudrenghien, P, Brunner, O, Butterworth, A, Linnecar, T, ...
The installation of the 400 MHz superconducting RF system in LHC is finished and commissioning is under way. The final RF system comprises four cryo-modules each with four cavities in the LHC tunnel...
Linac4 Technical Design Report (2006)
Arnaudon, L, Baudrenghien, P, Baylac, M, Bellodi, G, Body, Y, Borburgh, J, ...
Linac4 is an H- linear accelerator, intended to replace Linac2 as injector to the PS Booster (PSB). By delivering to the PSB a beam at 160 MeV energy, Linac4 will provide the conditions to double the...
Control of the LHC 400 MHz RF System (ACS) (2004)
Arnaudon, L, Disdier, M, Maesen, P, Prax, M
The LHC ACS RF system is composed of 16 superconducting cavities, eight per ring. Each ring has two cryomodules, each containing four cavities. Each cavity is powered by a 300 kW klystron. The...
Control of the LHC 400 MHz RF System (ACS) (2004)
Arnaudon, L, Disdier, M, Maesen, P, Prax, M
The LHC ACS RF system is composed of 16 superconducting cavities, eight per ring. Each ring has two cryomodules, each containing four cavities. Each cavity is powered by a 300 kW klystron. The...
The LEP RF Trip and Beam Loss Diagnostics System (2002)
Arnaudon, L, Olsen, R, Juillard, J C, Ciapala, Edmond, Beetham, G, Butterworth, A
During the last years of operation the number of operationally independent RF stations distributed around LEP reached a total of 40. A serious difficulty when running at high energy and high beam...
The LEP RF Trip and Beam Loss Diagnostics System (2002)
Arnaudon, L, Butterworth, A, Beetham, G, Ciapala, Edmond, Juillard, J C, Olsen, R
During the last years of operation the number of operationally independent RF stations distributed around LEP reached a total of 40. A serious difficulty when running at high energy and high beam...
The energy calibration of LEP in 1992 (2002)
Arnaudon, L, Assmann, R W, Billan, J, Birr, W, Blondel, A, Bobbink, Gerjan J, ...
Remote Data Acquisition for SPS 352 MHz Superconducting Cavities (1999)
The SPS Machine is equipped with four SuperConducting (SC) Cavities. These are used to accelerate the beams during the electron and positron cycles of LEP. During the last two years the control...
Remote Data Acquisition for SPS 352 MHz Superconducting Cavities (1999)
The SPS Machine is equipped with four SuperConducting (SC) Cavities. These are used to accelerate the beams during the electron and positron cycles of LEP. During the last two years the control...
Control of total voltage in the large distributed RF system of LEP (1995)
The LEP RF system is made up of a large number of independent RF units situated around the ring near the interaction points. These have different available RF voltages depending on their type and...
Accurate determination of the LEP beam energy by resonant depolarization (1995)
Arnaudon, L., Assmann, R., Blondel, A., Dehning, B., Grosse-Wiesmann, P., Jacobsen, R., ...
Accurate determination of the LEP beam energy by resonant depolarization (1995)
Arnaudon, L., Assmann, R., Blondel, A., Dehning, B., Grosse-Wiesmann, P., Jacobsen, R., ...
Accurate determination of the LEP beam energy by resonant depolarization (1994)
Arnaudon, L, Assmann, R W, Blondel, A, Dehning, Bernd, Grosse-Wiesmann, P, Jacobsen, R, ...
Recent achievements in transverse spin-polarization at LEP (1994)
Arnaudon, L, Assmann, R W, Blondel, A, Bouchet, B, Camas, J, Dehning, Bernd, ...
Effects of terrestrial tides on the LEP beam energy (1994)
Arnaudon, L, Assmann, R W, Blondel, A, Dehning, Bernd, Fischer, G E, Grosse-Wiesmann, P, ...
Effects of tidal forces on the beam energy in LEP (1993)
Arnaudon, L, Bordry, Frederick, Coosemans, Williame, Dehning, Bernd, Henrichsen, K N, Hofmann, A, ...
Measurement of the mass of the Z boson and the energy calibration of LEP (1993)
Arnaudon, L, Assmann, R W, Billan, J, Birr, W, Blondel, A, Bobbink, Gerjan J, ...
Measurement of the mass of the Z boson and the energy calibration of LEP (1993)
Arnaudon, L., Assmann, R., Billan, J., Birr, W., Blondel, A., Bobbink, G., ...
Measurement of the mass of the Z boson and the energy calibration of LEP (1993)
Arnaudon, L., Assmann, R., Billan, J., Birr, W., Blondel, A., Bobbink, G., ...
Measurement of the mass of the Z boson and the energy calibration of LEP (1993)
Arnaudon, L., Assmann, R., Billan, J., Birr, W., Blondel, A., Bobbink, G., ...
Measurement of the Mass of the Z-Boson and the Energy Calibration of Lep (1993)
Acton, P. D., Adriani, O., Abreu, P., Buskulic, D., Wachsmuth, H., Schmidt, R., ...
Measurement of the mass of the Z boson and the energy calibration of LEP (1993)
Arnaudon, L., Assmann, R., Billan, J., Birr, W., Blondel, A., Bobbink, G., ...
Measurement of the mass of the Z boson and the energy calibration of LEP (1993)
Arnaudon, L., Assmann, R., Billan, J., Birr, W., Blondel, A., Bobbink, G., ...
The energy calibration of LEP in 1991 (1992)
Arnaudon, L, Assmann, R W, Billan, J, Birr, W, Blondel, A, Bobbink, Gerjan J, ...
Energy calibration with a polarized beam at LEP (1992)
Arnaudon, L, Knudsen, L, Koutchouk, Jean-Pierre, Olsen, R, Placidi, Massimo, Schmidt, R, ...